Tuesday, May 15, 2018

We Must Pay Attention: D.E.P. To Hold Meeting For Community To Review Design For Gowanus Canal CSO Facility

I am encouraging begging everyone to attend a very important community meeting sponsored by the New York City Department of Environmental Protection and Council Member Stephen Levin on Thursday, May 17, 2018 to review the proposed design for the Gowanus Canal Combined Sewage Overflow facility at the head of the canal at Butler Street.

Why is this meeting important?

You may remember that D.E.P. is required by the U.S. Environmental Protection Agency to build an 8-million gallon sewage retention tank at the head-end of the Gowanus Canal as part of the Superfund clean-up to reduce the volume of untreated wastewater entering the waterway

D.E. P. has taken the requirement for a simple tank to a whole new level by over-designing, over-complicating, and over-spending with uncommon zeal for an agency that has happily allowed the canal to be used as an open sewer for decades and lobbied against the Gowanus Canal being declared a Superfund by E.P.A..

The cost of this tank has spiraled out of control. E.P.A. had estimated the cost of both the 8-million gallon and the cost for a smaller 4-million gallon in the middle section of the Canal at $77 million for both.
Because of D.E.P.'s insistance that the the 8-million gallon tank be constructed on private property instead of City-owned parkland as E.P.A. had suggested, the price tag has mushroomed.  D.E.P. has estimated the cost for land acquisition at $90 million alone, with an additional $400 million for the construction of the tank.
At a City Council hearing in March 2018, Kevin Clarke of D.E.P. spoke of a combined cost of $1.2 billion for both tanks.

Now, that is a crazy amount of money, prompting many in the community to wonder what D.E.P. is actually building: a simple retention tank or, as one local resident expressed, the Taj Mahal of sewer treatment facilities.

Now, keep in mind, the E.P.A. will have lots to say on the final design of the Gowanus facility at the head of the canal . However, the meeting on Thursday gives the community an opportunity to ask some real questions regarding run-away cost,  necessity of such an over-designed facility, the
protection of the iconic Gowanus Station building, a sweet old indutstrial brick structure situated on the project site and which D.E.P. wants to demolish despite calls from Gowanus residents to incorporate it into the final design. More broadly, we can ask what we actually get in return.

Lastly, it gives Gowanus residents a chance to ask D.E.P. about its other facility upgrade across from the canal: The Gowanus Canal Pumping Station and Flushing Tunnel that seems to be plagued by major design flaws. Since the station and the tunnel were put back into service a few years ago, massive amounts of foam has been created at the head of the canal. It is so bad, that the community has dubbed it the Gowanus"Cappuccino effect".
There is even foam oozing out of one of the buildings. And then there is the strange run-off that flows out of the pumping station.

Gowanus history should have taught us by now that D.E.P. has been more than negligent here in our community.  Let us ask the hard questions on Thursday's meeting. I will be there. Hope you will be there, too.

Below, a few photos of the Gowanus Cappuccino foam and strange leaks from the Gowanus Pumping Station, taken a few days ago.

Untitled
Untitled
Untitled
Untitled
Untitled
Untitled
Untitled
Untitled



Read more

Friday, June 05, 2015

Citibikes Are Coming To Our Neighborhood: Help Plan For The System

IMG_3945
The New York City Department Of Transformation will be hosting a Community Board 6 Bike Share Public Planning Workshop on Thursday, June 11th at 7 pm at PS 58 in Carroll Gardens.
Come to find out about the program and help DoT plan for expansion of Citibike into CB6 for the system here in our neighborhood.

The meeting is co-sponsor by Council Members Brad Lander, Carlos Menchaca, Ydanis Rodriguez, Borough President Eric Adams, State Senator Daniel Squadron, Assemblymember Jo Anne Simon, Brooklyn Community Board 6, Carroll Gardens Neighborhood Association, Cobble Hill Association, Park Slope Civic Council, and Park Slope Neighbors.



Read more

Tuesday, May 26, 2015

Reminder: Congresswoman Velázquez To Hold Public Meeting In Gowanus On Changes to National Flood Insurance Program's Preliminary Flood Insurance Maps And Rates

Gowanus Canal overflowing its banks during Hurricane

IMG_1498
***Reminder***
This Meeting Is This Thursday

Thank you to Congresswoman Nydia Velázquez, who is organizing a second public meeting, this time in Gowanus, regarding the changes to the National Flood Insurance Program's new preliminary flood insurance maps and rates.  The meeting will be held on Thursday, May 28 at 7 PM at 41 1st Street, in the community room of the Mary Star of the Sea Senior Apartments.

Here is why this meeting is important:
In the past few weeks, the Federal Emergency Management Agency (FEMA) sent out letters regarding updated flood maps for New York City to all property owners in or near the Special Flood Hazardous Area newly identified by the federal agency.

The Agency encourages everyone to identify their property's flood risk by checking the Preliminary 
Flood Insurance Rate Maps. The maps can be accessed here and here.

In the letter, FEMA stresses that the maps are only preliminary. A public comment and appeal period began on March 31st, 2015 and will continue until June 28th, 2015. During this period, homeowners can challenge FEMA's new maps by sending technical and/or scientific data regarding their individual property.
After FEMA evaluates all challenges and appeals, the new maps will be incorporated and flood insurance purchase requirements will go into effect.

If you received the FEMA letter because your property is either is zone A or Zone X, you need to take the time to understand what all of this will mean. This has some very important ramifications beyond getting flood insurance.

If you need legal help regarding this issue:
Two weeks ago, I was contacted by Antony Gemmell, Staff Attorney for New York Legal Assistance Group, a non-profit organization which provides free legal services to people who were impacted by Superstorm Sandy.
Gemmell let me know that New York Legal Assistance Group "offers advice and representation on a wide range of legal issues related to Sandy, including flood insurance."
Please avail yourself of the organization's services by contacting NYLAG's Storm Response Unit (SRU) client intake team at (212) 584-3365 or stormhelp@nylag.org.



Read more

Saturday, May 16, 2015

NYC DEP Willing To Depend On Eminent Domain To Solve Gowanus Drainage Problems

IMG_4002
IMG_3995
IMG_4001
New York City Department of Environmental Protection Commissioner Emily Lloyd
IMG_4017 1
NYC DEP Deputy Commissioner Angela Licata
IMG_3996
IMG_4018 1
IMG_3998
IMG_4020 1
NYC DEP  assistant Commissioner Jim Mueller
Screen Shot 2015-05-16 at 6.34.37 PM
DEP short list for RH-034 CSO Tank siting
IMG_4023 1
New York City Department Of Environmental Protection (DEP) Commissioner Emily Lloyd came to PS 32 on Hoyt Street on Thursday evening to present the second in a series of meetings related to the Combined Sewer Overflow Long Term Control Plan for the Gowanus Canal.

As you may know, the City diverts raw sewage mixed with rainwater directly into the Gowanus Canal and other water bodies during rain events, when our sewage treatment facility is overburdened. This violates the Clean Water Act of 1972.

In addition, the Environmental Protection Agency, as part of its Superfund investigation of the Gowanus Canal, has identified the City as the second largest Potentially Responsible Party (PRP) for discharging "hazardous substance-contaminated untreated sewage" into the canal.

Thursday night's presentation by Commissioner Lloyd focused on the work the City has already completed to address the CSOs and what measures it will implement in the future.

The Gowanus gray infrastructure improvements that have already been undertaken include upgrades to the  Gowanus Pumping Station and  to the Flushing Tunnel.
The Gowanus Pumping Station was put back into operation in June 2014. According to DEP,  the upgrades have increased pumping capacity from 20 to 30 million gallons per day.
Since May 2014, the three pumps at the Flushing Tunnel are operating, which has increased the flow through the tunnel, and improved dissolved oxygen in the water.

Further, the DEP is investing in green infrastructure in Gowanus. So far the agency has built 18 bioswales, has installed porous pavement installation at 4th Street and 5th Avenue, installed a porous playground surface at PS 261.  The Agency has provided a grant towards the Gil Hodges Community Garden's storm water management system.  90 more bioswales and 2 storm water green streets are currently under construction. 

Commissioner Lloyd also spoke about the location of two CSO retention tanks that the EPA is requiring the City to construct in order to protect its remedy for the Gowanus Canal. Construction of these retention tanks is an important part of the remedial design. As per the EPA, the tanks are "combined sewer overflow (CSO) control measures for the upper reach of the Canal to significantly reduce overall contaminated solid discharges to the Canal." The retention tanks will retain discharges from two of the largest outfalls in the canal, RH-034 and OH-007 and will reduce the CSO in the canal by 58% to 74%. 
According to the Federal Agency,"it is estimated that an 8-million gallon tank and a 4-million gallon tank shall be required to address CSOs from outfalls RH-034 and OH-007, respectively."

Though the EPA had suggested two sites for the retention tanks, the agency was willing to discuss alternative locations.  The City has until June 30 to make a final site decision.
Commissioner Lloyd explained: "There are two things the EPA told us we could evaluate: one is the locations for those two tanks, and the other was that we could look at alternative sizes for the tanks if we thought we could achieve the 58% to 74% reduction goal with some alternatives other than the tanks.  So we have been looking at those. We are not complete with our evaluation, but we think we are getting close."

DEP is considering two sites for the retention tank for outfall RH-034. The first site are two privately owned lots directly adjacent to the canal between Douglass Street and DeGraw Street.  The second location is directly across the street at Thomas Greene Park.
"Between those two sites, we think we are likely to recommend the first site," Commissioner Lloyd told the community. "The reasons for that are emerging. First,  because of its proximity to the rest of our infrastructure, it will be more efficient to construct and operate.  The second reason is that if we go to the park site, we will need a surface building to manage the mechanics and because of potential storm surges, it can't be low. So we have to go up and we are concerned that it will cover significant portions of the park. This means that during construction of the tank, we would disrupt most of the park."
She added:"We and the Parks Department are extremely concerned and very reluctant to lose that piece of parkland."
Lloyd indicated that even with the cost of acquiring the privately owned sites, it still would be cost effective.

The DEP also looked at two sites for outflow OH-007 in the middle of the canal.  The agency seems to have settled on the site known as the 'Salt Lot' near the 5th Street turning basin, which is owned by the Department of Sanitation.  "It is likely that  that is the one we will recommend to the EPA, unless something turn up in our analysis from now till the end of June that surprises us," Lloyd said.
She added: "There is one other alternative that we are looking at concerning the OH-007 outflow. There is some excess capacity in the sewer system going to Owl's Head [sewer treatment plant], beyond the canal.  We are looking if we can divert flow from OH-007 into the sewer lines to Owl's Head."

Mysteriously, the DEP seems to have found so many ways to capture rainwater in and around the Gowanus watershed, that the agency is now trying to reduce the size of the EPA-mandated tanks from
an 8 million gallon tank to a 3.5 or 5.7 million gallon tank at RH-034, and from a 4 million gallon tank at OH-007 to a 1.4 or 2.5 million gallon tank. (see chart above).
Lloyd explained that the smaller tanks, according to DEP calculations would achieve the 58% to 74% CSO reduction mandated by the EPA.  "An 8 million gallon tank would achieve 82% reduction, which is above what EPA set as as a goal. We are always looking to see if we can meet targets in the canal at a less costly level."

After the presentation, the community had a chance to ask questions.

Asked if DEP is looking at population projections and the effect of new development on the retention tanks and sewage capacity,  Lloyd simply replied: "yes, we are doing population projections in the area."

My question related to the siting of the larger tank at the head of the canal and DEP's preference to locate it on private property instead of placing it on park land that it already owns.
"Have you talked to the owners of the property? Have you negotiated a price? Are they willing to sell?  If they do not want to sell, does that mean you need to take the land by eminent domain, which is going to take a long, long time?  Is that a delaying tactic by the City?" I asked.
Her answer:
"Yes, we have spoken to them.  We know what the fair market value of the land is.  Yes, if they are unwilling to sell and that is the selected site, we will proceed to eminent domain. We actually think that this can be expedited and we think that we can accomplish that much quicker than doing the work on the [Thomas Greene] park site."

It will be interesting to see what calculations DEP is using to make the argument that using eminent domain to site the tank at RH-034 is as cost effective and timely as placing it on parkland that it already owns.

One can only imagine what the EPA will think of DEP's  suggestion.
The Federal Agency, in its Record of Decision, which represents a blueprint for the cleanup of the Gowanus Canal,  had suggested Douglas Greene Park and the pool as the preferred site for the tank.
The EPA reasoned that:
- the park is one of the only open pieces of land in this densely populated area. 
-the land is already owned by New York City.
-Thomas Greene Park was constructed over the former Fulton Municipal Works Manufacturing Plant (MGP), which operated on the site from 1879 to 1929. Today, the land underneath the park is still heavily contaminated with coal tar. Since some of this free liquid tar is moving towards the canal, National, Grid, which bought Brooklyn Union Gas/National Grid in 2006, needs to address the problem. The work will be done under NYS Department of Environmental Conservation supervision.

The EPA logically concluded that constructing the tank under the swimming pool area of the park could be combined with the remediation work.

Recently, the DEC released its proposed Environmental Remediation plan. The primary components of the remedy "are the construction of a sealed wall along the western shoreline of the Gowanus Canal and the removal of any coal tar that accumulates behind it." 
They appear to be willing to let National Grid off the hook to clean up the former Fulton site until "an opportunity presents itself".  Many wonder if we are missing an opportunity right now, with EPA in charge of a massive remediation.  We should be outraged that once again this can is kicked down the road for our children and grandchildren to clean up.

So, there you have it reader, we await the final decision of our city and state and hope that they are fully seizing this opportunity to finally clean up our polluted neighborhood and to cooperate with the EPA.  We will know for sure in less than two months.


PS:
I also mentioned the suds that have been covering the Gowanus Canal lately. The problem seems to originate at the top of the canal near the flushing tunnel at Douglass Street. It would appear that the three new pumps which the DEP has installed introduce massive amounts of air and movement into the water, which could be stirring up household soaps and fats, which end up in the Gowanus by way of the CSO outflow right next to the flushing tunnel. The effect has become known to many in the Gowanus community as the 'milkshake' effect.
Since we have mostly had dry weather this spring, I asked Emily Lloyd if that was an indication that sewage was flowing into the canal even when there were no rain events."Not to give a definitive answer tonight, but we don't think this is from the CSO," Commissioner Lloyd answered. "We really think that it is the aeration coming from Buttermilk Channel. That's a very aerated flow that is coming in, and we think that as it comes in, it churns up. That is our preliminary thought at this point."


Photos illustrating the 'Gowanus milk shake effect" taken a few days ago by Reader Andrew
IMG_3446
IMG_3450-2



Read more